full transcript
From the Ted Talk by Alex Gendler: Blood, concrete, and dynamite Building the Hoover Dam
Unscramble the Blue Letters
Before construction on the dam could begin, the entire river had to be roreuted. bdluinig these diversion tunnels rqieerud balstnig into each side of the canyon to create 17 meter tall tubes. With a combined ltnegh of almost 5 kilometers, these tunnels could divert roughly 5,600 cubic meters of water per second. However, workers faced grueling conditions to finish these on time, and dozens succumbed to the scorching heat.
By the fall of 1932, the river had been successfully redirected. But the most dangerous work was still ahead. Over 1 million cubic meters of loose rock neeedd to be cealred from the canyon wllas. So foremen brought in high scalers who deedenscd the cliffs on ropes, removing rubble with jackhammers and daimtnye. From circus aocbrtas and former sailors, to local Apache, these death-defying individuals performed some of the most dangerous— and glamorous— work on site.
Open Cloze
Before construction on the dam could begin, the entire river had to be ________. ________ these diversion tunnels ________ ________ into each side of the canyon to create 17 meter tall tubes. With a combined ______ of almost 5 kilometers, these tunnels could divert roughly 5,600 cubic meters of water per second. However, workers faced grueling conditions to finish these on time, and dozens succumbed to the scorching heat.
By the fall of 1932, the river had been successfully redirected. But the most dangerous work was still ahead. Over 1 million cubic meters of loose rock ______ to be _______ from the canyon _____. So foremen brought in high scalers who _________ the cliffs on ropes, removing rubble with jackhammers and ________. From circus ________ and former sailors, to local Apache, these death-defying individuals performed some of the most dangerous— and glamorous— work on site.
Solution
- rerouted
- acrobats
- required
- descended
- building
- walls
- dynamite
- needed
- blasting
- cleared
- length
Original Text
Before construction on the dam could begin, the entire river had to be rerouted. Building these diversion tunnels required blasting into each side of the canyon to create 17 meter tall tubes. With a combined length of almost 5 kilometers, these tunnels could divert roughly 5,600 cubic meters of water per second. However, workers faced grueling conditions to finish these on time, and dozens succumbed to the scorching heat.
By the fall of 1932, the river had been successfully redirected. But the most dangerous work was still ahead. Over 1 million cubic meters of loose rock needed to be cleared from the canyon walls. So foremen brought in high scalers who descended the cliffs on ropes, removing rubble with jackhammers and dynamite. From circus acrobats and former sailors, to local Apache, these death-defying individuals performed some of the most dangerous— and glamorous— work on site.
Frequently Occurring Word Combinations
ngrams of length 2
collocation |
frequency |
hoover dam |
2 |
colorado river |
2 |
canyon walls |
2 |
diversion tunnels |
2 |
cubic meters |
2 |
Important Words
- acrobats
- apache
- blasting
- brought
- building
- canyon
- circus
- cleared
- cliffs
- combined
- conditions
- construction
- create
- cubic
- dam
- dangerous
- descended
- diversion
- divert
- dozens
- dynamite
- entire
- faced
- fall
- finish
- foremen
- grueling
- heat
- high
- individuals
- jackhammers
- kilometers
- length
- local
- loose
- meter
- meters
- million
- needed
- performed
- redirected
- removing
- required
- rerouted
- river
- rock
- ropes
- roughly
- rubble
- sailors
- scalers
- scorching
- side
- site
- successfully
- succumbed
- tall
- time
- tubes
- tunnels
- walls
- water
- work
- workers